Hull Street over Manchester Canal Bridge Replacement

Project Summary and Scope

Replacement of structurally deficient bridge on Hull Street over Manchester Canal 

VDOT UPC 113290

Project Milestones

Scoping underway

Section 106 Coordination underway

Project Funding

Project Estimate - $ 10,761,323

 

City GO Bonds -  $ 2,502,000

VDOT Revenue Sharing - $ 2,502,000

State of Good Repair - $ 3,967,000

Total  $ 8,971,000

 

To be funded  $ 1,790,323

 

 

Project Status Updates

Met with Verizon to discuss relocation of their facilities off of bridge.  City to grant Verizon a utility easement.

Section 106 Coordination ongoing.

Section 408 Coordination with Army Corp of Engineers underway.

 

Documents

Conceptual Plans (dated Jan 2021)

Public Information outreach was held April 7, 2022 to May 12, 2022, comments and responses posted here

Planning Commission conceptual approval here

City to grant Verizon an utility easement on City property  O&R

Permits

 

Expenses

 

Project Contact Information, if you have questions about this project please contact this individual.

Project Overall Status (Active, Pending or Complete)

Active

Ordinance Information

 CAO authorized to execute a standard project agreement

City to grant Verizon an utility easement on City property

Contract Information

N/A