Mayo Bridges Rehabilitation

Project Summary and Scope

Replacement of Mayo Bridges over James River

Project Milestones

Mayo Bridge – From VDOT on June 20, 2023

The current actives are as follows:

  • Architectural and Historical surveys are taking place Summer 2023
  • The procurement of a consultant who will perform a geotechnical/structural study of the existing piers is finalizing, and expect them to be on site Summer 2023

Next immediate actives are as follows:

  • Procurement of the consultant (same as above) to complete the conceptual concepts/PFI level work including the first public involvement (10% level) anticipated to be Summer 2023
  • Initial public involvement anticipated to be Fall 2023

Future actives (long term, major milestones) are as follows:

  • UDC Conceptual Meeting and finalize project scoping anticipated early 2024
  • Public Hearing anticipated to be mid 2024
  • DB Procurement anticipated to be late 2024
  • Construction Start anticipated to be 2025 for approximately 3 years

Mayo Bridge – From VDOT on August 28, 2023

The current actives are as follows:

  • Architectural and Historical surveys are complete, though follow-up may be necessary once the report is reviewed

  • Geotechnical survey of the bridge sub-structure is underway

  • Sub-structure analysis and validation underway

 

Next immediate actives are as follows:

  • HAZMAT survey of the bridge utilities late September

  • Procurement of the consultant (same as sub-structure analysis) to complete the conceptual concepts/PFI level work including the first public involvement (10% level) anticipated to be Fall 2023

  • Initial public involvement anticipated to be late 2023 or early 2024

Future actives (long term, major milestones) are as follows:

  • UDC Conceptual Meeting and finalize project scoping anticipated mid 2024

  • Public Hearing anticipated to be late 2024

  • DB Procurement anticipated to be 2025

  • Construction Start anticipated to be 2026 for approximately 3 years

Project Schedule

Project is VDOT administered

 

Project Funding

Project Estimate - $ 90,000,000

 

VDOT Six Year Improvement Plan

 

Project Status Updates

VDOT project administration agreement executed 2023.01.17

 

VDOT presentation to the City Urban Planning Commission:

UDC Meeting Record

VDOT Mayo Bridge Presentation to UDC 2023.02.09

 

Permits

 

Expenses

City Match to VDOT   $ 103,536.00

 

Project Contact Information, if you have questions about this project please contact this individual.

Project Overall Status (Active, Pending or Complete)

Active

Ordinance Information

Ord 2022-319

Contract Information

N/A