Construction of a New City Hall

Project Summary and Scope

This project will identify a site and construct a new seat of government. The existing City Hall located at 900 E. Broad Street is over 50 years old and for decades has been showing signs of deterioration. There has been countless ongoing sprinkler, HVAC, cooling tower, electrical and plumber issues that continue to plaque facility maintenance with astronomical cost.

An architectural firm has been contracted to develop a space needs assessment to determine square foot needs for a new edifice and determine occupants of the new seat of government.

Project Milestones

The space programming has been completed.

Project Funding

FY23 Capital Planning, Next Phase TBD

Project Status Updates

Moseley has completed the conceptual plan and COR has approved the conceptual plan.  No location has been determined.

Permit, information is listed below.  For details, please call the Department of Planning Development and Review at 804-646-4169.

Not applicable at this time. Still in programming stage.

Expenses (costs are reported quarterly)

March 2024 actual and encumbered expenditures to date: $1,646,908

Project Contact Information, if you have questions about this project please contact this individual.

For information about the details of any project first contact the public information office for the department running the project.  For most projects the following people can help:

Project Overall Status (Active, Pending or Complete)

Pending

Ordinance Information

Not applicable at this time. Still in programming stage.

Contract Information

Moseley Architects has been contracted to prepare the space needs assessment and concept design study.